Track Improvements 2 Week Schedule

Home Forums Thunder Mountain Track Talk Track Improvements 2 Week Schedule

This topic contains 0 replies, has 1 voice, and was last updated by  Merv 4 months, 2 weeks ago.

Viewing 1 post (of 1 total)
  • Author
    Posts
  • #5237

    Merv
    Participant

    Update May7, 2017

    Weekend of May 12 – 14  – Clearing emergency shutdown of trees, shrubs, rocks, etc.. Line up shutdown with the track. Expand, level, gravel all pit areas, excavate foundations for light standards, trench water ditches, general cleanup.

    Week of May 15 – 19 – Milling 14 feet wide asphalt in both lanes, install 330 foot sensor conduit, lay and compact new high traction asphalt.

     